Installation Requirements for ZJ Series Slurry Pumps

×

Installation Requirements for ZJ Series Slurry Pumps
(1) Pre-Installation Checks
Verify the model, parameters, and component completeness. Review the technical manual before installation.
(2) Alignment
For horizontal pumps, use a two-stage grouting method. Ensure:
Centerline alignment with the foundation (±2 mm tolerance).
Levelness within 0.1/1000.
Coupling Alignment Methods:
Straightedge and Feeler Gauge: Max. misalignment ≤ 0.10 mm.
Dial Indicator: Runout ≤ 0.15 mm; gap variance ≤ 0.10 mm.
For belt-driven units, maintain parallel shaft alignment via pulley adjustment.
(3) Piping Configuration
Inlet Pipe: Match or slightly exceed pump inlet size to prevent cavitation/sedimentation. Include a gate valve and expansion joint.
Outlet Pipe: Match pump outlet size. Install a gate valve and pressure gauge upstream of the first valve.
Key Rule: Throttle flow only at the outlet—never the inlet—to avoid cavitation.
(4) Seal/Cooling Water Lines
For mechanical seals, connect water lines per manual (pressure gauge side = inlet).
Grease-lubricated bearings require no cooling water.

prev
Slurry Pump Performance Curves What is a performance curve? What does it include, and usage?
Common faults and solutions of abrasion resistant and explosion proof mining multistage pumps
next
recommended for you
no data
Get in touch with us
Ready to work with us ?

Our professional slurry pump team is always At your services.

We are engaged in the manufacturing and producing of heavy duty and severe duty slurry pumps and spare parts.
Every CNSME product comes with an industryeading promise to weather years of memories.
Safe, fast, and on-time delivery.
no data
Contact Us

Contact: Ms.Serena Zhang

Tel: +86 13333119820

Email: sales@cnsmepump.com 

WhatsApp: +86 13333119820

Add: 260# West Huaian Road, Shijiazhuang, Hebei, China. 050051.

Download
Copyright © 2025 Shijiazhuang Minerals Equipment Co., Ltd.  | Sitemap

Send your inquiry

弹窗效果
Customer service
detect